The Municipality of Central Elgin will be completing the second phase of the Port Stanley Storm Sewer Upsizing project in September 2026. This initiative is funded in part by the Government of Canada through the Disaster Mitigation and Adaptation Fund and by the Government of Ontario through the Municipal Housing Infrastructure Program – Health and Safety Water Stream. The Port Stanley Storm Sewer Upsizing project addresses known storm water capacity deficiencies that contribute to localized flooding, surface ponding, and strain on existing infrastructure within the Port Stanley area. The project reduces the risk of roadway flooding and service disruptions, thereby improving public safety and system reliability during significant rainfall events.
PROJECT SCOPE
Phase 1B of the Port Stanley Storm Sewer Upsizing project involves the construction of new storm sewers, replacement of water services, asphalt road surface renewal, and new concrete curb and gutter on Maud Street and Bessie Street.
Alongside the Municipality’s infrastructure work, Enbridge will be renewing their gas main and services lines on Maud Street and Bessie Street and ERTH Power will be relocating utility poles on Maud Street only. These utility works are underway and will be completed prior to the storm sewer works commencing. The natural gas line and hydro pole work is being completed by the utility company or their subcontractor and is not under the management of the Municipality.
PROJECT SCHEDULE
The construction schedule for Phase 1B has been intentionally planned to avoid the tourist high season for safety, construction efficiency, and with consideration to local businesses and residents. Construction will occur between September 8 and November 20, 2026. The activities on Maud Street and Bessie Street will be staged where excavation work on Bessie Street will not commence until Maud Street has been restored to a functional gravel driving surface.
PROJECT AREA
The Municipality of Central Elgin will be completing the second phase of the Port Stanley Storm Sewer Upsizing project in September 2026. This initiative is funded in part by the Government of Canada through the Disaster Mitigation and Adaptation Fund and by the Government of Ontario through the Municipal Housing Infrastructure Program – Health and Safety Water Stream. The Port Stanley Storm Sewer Upsizing project addresses known storm water capacity deficiencies that contribute to localized flooding, surface ponding, and strain on existing infrastructure within the Port Stanley area. The project reduces the risk of roadway flooding and service disruptions, thereby improving public safety and system reliability during significant rainfall events.
PROJECT SCOPE
Phase 1B of the Port Stanley Storm Sewer Upsizing project involves the construction of new storm sewers, replacement of water services, asphalt road surface renewal, and new concrete curb and gutter on Maud Street and Bessie Street.
Alongside the Municipality’s infrastructure work, Enbridge will be renewing their gas main and services lines on Maud Street and Bessie Street and ERTH Power will be relocating utility poles on Maud Street only. These utility works are underway and will be completed prior to the storm sewer works commencing. The natural gas line and hydro pole work is being completed by the utility company or their subcontractor and is not under the management of the Municipality.
PROJECT SCHEDULE
The construction schedule for Phase 1B has been intentionally planned to avoid the tourist high season for safety, construction efficiency, and with consideration to local businesses and residents. Construction will occur between September 8 and November 20, 2026. The activities on Maud Street and Bessie Street will be staged where excavation work on Bessie Street will not commence until Maud Street has been restored to a functional gravel driving surface.
Share Construction Update - Week of October 22 on FacebookShare Construction Update - Week of October 22 on X (formerly Twitter)Share Construction Update - Week of October 22 on LinkedinEmail Construction Update - Week of October 22 link
Bessie Street Construction and Parking
Construction on Bessie Street began Monday, October 20, following asphalt removal on Thursday and Friday.
Residents are asked to use one of the municipal parking lots identified in the construction notice for parking during construction.
Maud Street Curb Work
Residents on Maud Street may notice stakes and string lines being installed near the front of properties as contractors prepare for the upcoming curb work.
Please use caution when walking near the work area. Stakes and string lines may present a tripping hazard, so please watch your step when travelling through the area.
Curb pouring is tentatively scheduled for Tuesday or Wednesday next week, weather permitting.
Thank you for your patience and cooperation as work continues on this project.
Bessie Street Construction and Parking
Construction on Bessie Street began Monday, October 20, following asphalt removal on Thursday and Friday.
Residents are asked to use one of the municipal parking lots identified in the construction notice for parking during construction.
Maud Street Curb Work
Residents on Maud Street may notice stakes and string lines being installed near the front of properties as contractors prepare for the upcoming curb work.
Please use caution when walking near the work area. Stakes and string lines may present a tripping hazard, so please watch your step when travelling through the area.
Curb pouring is tentatively scheduled for Tuesday or Wednesday next week, weather permitting.
Thank you for your patience and cooperation as work continues on this project.
Share Construction Update - Week of September 21 on FacebookShare Construction Update - Week of September 21 on X (formerly Twitter)Share Construction Update - Week of September 21 on LinkedinEmail Construction Update - Week of September 21 link
The contractor has started water service replacements on Maud Street as part of the Phase 1B project.
Residents may experience temporary water service disruptions while this work is underway. The contractor will notify affected residents directly in advance of any planned water service disruptions.
Thank you for your patience and understanding as this important work continues.
The contractor has started water service replacements on Maud Street as part of the Phase 1B project.
Residents may experience temporary water service disruptions while this work is underway. The contractor will notify affected residents directly in advance of any planned water service disruptions.
Thank you for your patience and understanding as this important work continues.
Share Construction Update - Week of September 14 on FacebookShare Construction Update - Week of September 14 on X (formerly Twitter)Share Construction Update - Week of September 14 on LinkedinEmail Construction Update - Week of September 14 link
Phase 1B construction is underway on Maud Street and Bessie Street. This week, crews are peeling back the existing asphalt and working to dewater the main watermain line in preparation for watermain work next week.
Parking reminder: Now that construction has started, residents should use the Lotus Lane parking lot and display the provided parking pass. If you have not received a parking pass, please see Jeremy, the Central Elgin representative on site to get a pass.
Internet service: During construction, there may be times when internet service is disrupted. If this happens, please contact your internet provider directly. Internet providers will need to verify your account details and address information, which the contractor does not have access to.
Phase 1B construction is underway on Maud Street and Bessie Street. This week, crews are peeling back the existing asphalt and working to dewater the main watermain line in preparation for watermain work next week.
Parking reminder: Now that construction has started, residents should use the Lotus Lane parking lot and display the provided parking pass. If you have not received a parking pass, please see Jeremy, the Central Elgin representative on site to get a pass.
Internet service: During construction, there may be times when internet service is disrupted. If this happens, please contact your internet provider directly. Internet providers will need to verify your account details and address information, which the contractor does not have access to.
Share Phase 1B Presentation - Recorded on FacebookShare Phase 1B Presentation - Recorded on X (formerly Twitter)Share Phase 1B Presentation - Recorded on LinkedinEmail Phase 1B Presentation - Recorded link
Share Public Information Center - Date Change on FacebookShare Public Information Center - Date Change on X (formerly Twitter)Share Public Information Center - Date Change on LinkedinEmail Public Information Center - Date Change link
Please note: change of date to the Public Information Center (PIC) for the Port Stanley Storm Sewer Upsizing – Phase 1B project.
The PIC will now be held on August 20, 2026 at the Port Stanley Arena upper mezzanine at 5:30 p.m. to 7:00 p.m. We apologize for any inconvenience this may cause.
The scope and schedule for the project remain unchanged.
Please note: change of date to the Public Information Center (PIC) for the Port Stanley Storm Sewer Upsizing – Phase 1B project.
The PIC will now be held on August 20, 2026 at the Port Stanley Arena upper mezzanine at 5:30 p.m. to 7:00 p.m. We apologize for any inconvenience this may cause.
The scope and schedule for the project remain unchanged.
Share Construction Tender Awarded on FacebookShare Construction Tender Awarded on X (formerly Twitter)Share Construction Tender Awarded on LinkedinEmail Construction Tender Awarded link
Cassidy Construction London Ltd. has been selected to complete the Port Stanley Storm Sewer Upsizing- Phase 1B project.
Click here to play video
Phase 1B Recorded Presentation
Presentation outlines project overview, schedule, project impacts, project communication and potential change in traffic movement.
This project is funded in part by the Government of Canada through the Disaster Mitigation and Adaptation Fund and the Province of Ontario through the Municipal Housing Infrastructure Program – Health and Safety Water Stream.
The Port Stanley Flood Mitigation is a series of projects to improve stormwater infrastructure that increase resiliency from current and potential future large scale climate change storm events.