Southdale Line Reconstruction

Share on Facebook Share on Twitter Share on Linkedin Email this link

The Southdale Line Reconstruction project is a joint project between the Municipality of Central Elgin and the City of St. Thomas. The project is located to the west of Sunset Drive and extends about 500m west along the boundary area between St. Thomas and the Municipality. The road updates include access to the future Kemsley Farm Subdivision and future connection to the Shaw Valley Subdivision.

The project scope includes installation of new watermain and water service connections, new sanitary sewer main and sanitary sewer service connections, new storm sewer service connections, a widened urban road cross section with sidewalks on the south side and designated bike lanes, and updated train track crossing.

Bre-Ex Limited will be the Contractor for this project.

The Southdale Line Reconstruction project is a joint project between the Municipality of Central Elgin and the City of St. Thomas. The project is located to the west of Sunset Drive and extends about 500m west along the boundary area between St. Thomas and the Municipality. The road updates include access to the future Kemsley Farm Subdivision and future connection to the Shaw Valley Subdivision.

The project scope includes installation of new watermain and water service connections, new sanitary sewer main and sanitary sewer service connections, new storm sewer service connections, a widened urban road cross section with sidewalks on the south side and designated bike lanes, and updated train track crossing.

Bre-Ex Limited will be the Contractor for this project.

  • Southdale Line Road Paving Update

    Share on Facebook Share on Twitter Share on Linkedin Email this link
    20 days ago

    Bre-Ex Ltd. is currently preparing the road granulars for asphalt pavement. During this time, there will be intermittent access to your driveway while the workers make the appropriate adjustments. Del-Ko Paving will be onsite Monday, July 20th to place HL-8 base asphalt on the full extend of the project area. They will then proceed with placing driveway asphalt on Tuesday and Wednesday. When the asphalt is placed on the driveways, please avoid rotating the tires of your vehicle while in a stationary position.

  • Concrete Curb To Be Placed on July 6, 2020

    Share on Facebook Share on Twitter Share on Linkedin Email this link
    about 1 month ago

    Notice to residents on Southdale Line, a concrete curb will be placed on Monday, July 6th.

  • Road Reconstruction Update

    Share on Facebook Share on Twitter Share on Linkedin Email this link
    about 2 months ago

    Bre- Ex Ltd. has now completed the installation of the Sanitary Sewer and the new water main along Southdale Line. There are a few issues they need to correct prior to completing the granular road base. Work on site has stopped temporarily as Bre-Ex arranges for the manpower and equipment necessary to correct the issues. It is anticipated that curb, gutter and asphalt will be placed in the next 3 weeks. A letter will be hand delivered to the residents on Southdale Line regarding the construction of the concrete curb and sidewalk and how that will affect access to driveways.

  • Project Commencement

    Share on Facebook Share on Twitter Share on Linkedin Email this link
    5 months ago

    Bre-Ex will be onsite and actively working on the project on March 2nd. During the first week, the PSTR tracks will be removed. Please use Lyndale Avenue to access Southdale Line on the west side of the tracks.

  • Notice of Construction Letters Sent Out

    Share on Facebook Share on Twitter Share on Linkedin Email this link
    by Shannon Zylstra, 6 months ago

    We've sent out letters of construction to residents directly impacted by this project on Southdale Line (ground zero). A secondary notice, has been sent out to residents on Lyndale Avenue and further west on Southdale Line to inform them of the nearby project.

    (You may see this letter in the Documents section of this page)